“How long will this take?” comes up in nearly every first consultation at Veda, right alongside budget. It deserves a real answer, not the vague “a few weeks” that undersells what actually goes into a full kitchen renovation done properly.
Homeowners are planning around this timeline in real, practical ways – arranging temporary kitchen setups, coordinating with other renovation work, or timing around family events. A vague answer leaves people planning against a number that turns out to be wrong, which causes more frustration than an honest, detailed breakdown upfront.
| Phase | Typical duration |
| Design consultation and concept development | 1-2 weeks |
| Detailed design, material selection, and final approval | 2-3 weeks |
| Precise on-site measurement | A few days, once layout is finalized |
| Manufacturing (cabinetry, custom elements) | 4-8 weeks, depending on complexity and materials |
| Installation | 1-2 weeks for a standard full kitchen |
| Snagging and final adjustments | 3-7 days |
Total project time from first consultation to handover typically runs 8-14 weeks for a standard full kitchen renovation, with more complex or custom projects extending beyond that range.
Veda’s process starts with an in-depth consultation to understand layout needs, style direction, and any hard timeline constraints, followed by design development, precise measurement, and manufacturing scheduled with realistic lead times communicated upfront rather than optimistic estimates. See our kitchen renovation cost post for the budget side of planning, or our kitchen renovation mistakes post for pitfalls worth avoiding during the process itself.
A standard full kitchen renovation typically takes 8-14 weeks from initial consultation to final handover, though custom materials or structural changes can extend this timeline.
Generally not for the installation phase itself, though earlier design and manufacturing phases don’t require the kitchen to be out of use – planning a temporary setup for the installation period is recommended.
Common causes include custom or imported material lead times, mid-process design changes after manufacturing has started, structural work complications, and building access or coordination restrictions in managed properties.